|
|
|
DATE
|
DESCRIPTION
OF REPAIR or CONSERVATION ACTION
|
| 1820 |
Marble
blocks sawed with iron-blade saws and wet sand. Columns fluted
and rubbed. Ashlar siding rubbed (1962
HSR). “Rubbed”
refers to honing the stone to a smooth surface with either an abrasive
block made of sandstone or a hard rock with wet sand (McKee, 1973).
|
|
1840
|
Removal
of marble retaining wall and erection of flight of stairs along
Chestnut Street.
|
|
1844
|
Strickland
called in to renovate building. Floors white washed, fireplaces
removed, roof repaired, interior marble columns and architraves
scrubbed with pumice stone (Letter from William Strickland to Collector
Judge Blythe, 9 December 1844, INHP archives). Architect
proposed that the building by cleaned by one or two permanent laborers,
but no evidence was found that the advice was carried out. Strickland
mentioned that several laborers periodically cleaned the building
while it was being used as a bank (Letter
from William Strickland to Collector Judge Blythe, 13 December 1844,
INHP Archives).
|
|
1850
|
Two
windows on first floor of north portico substituted for the marble
slabs of sham doors that were part of the original design. Brick
foundation for marble steps on the north portico was
reset. The flagstones of terrace were reset and repointed.
|
|
1860
|
Terrace
removed.
|
|
1864
|
Three
south windows on the second floor of both the east and west sides
were enlarged and extended into the architrave by inserting an additional
sash above the normal window level. Small windows added to
the second floor of the central projection of east and west exterior
walls.
|
|
1864-1872
|
Extensive
alteration carried out on the interior under the supervision of
John McArthur, Jr.
|
|
1865
|
One
financial record gave an exacting accounting of recent outlays for
materials and services rendered. Among those outlays, one was
paid out 1
March 1865
to Edwin A. Smith for supplying ‘lime cement’ at a cost of $516.45
(Letter from Superintendent John Reir
to Acting Assistant Architect B. Bertly,
INHP Archives).
|
|
1868
|
Removal
of brick partitions from underneath the north portico and installation
of iron door at entrance.
|
|
1873
|
Carved
interior marble was rubbed clean (Letter from the Superintendent
of Public Buildings John McArthur to Supervising Architect for the
Treasury Department A.B. Mullett, 7 January 1873,
INHP Archives).
|
|
1922
|
Loose
stone removed from columns prior to 1 September 1922.
The Obelisk Waterproofing Company of New York and the Arvon
Company of Philadelphia called in
to give estimates for waterproofing the entire exterior of the Second
Bank. The surviving correspondence shows only the estimate from
the Obelisk Company (Correspondence between the consulting architect,
the Supervising Architect, and Obelisk, 11 August 1922, AIA Archives and Library, Washington, DC). A 1940 photograph
shows the building heavily and uniformly soiled, which may
be explained by the hot wax treatment that the Obelisk Company
advocated (Old Philadelphia Custom House, 1947, INHP Archives).
|
|
1923
|
Recommendations
made to clean and repoint the building
with soap and water and “a good stiff brush.” Several pieces of
marble fell off “from disintegration,” especially on the columns.
Also endorsed was the idea of using “a waterproofing compound.
This could do no harm and might prove a real preservative.” (Letter from architect Edward Crane to Supervising Architect James
A. Wetmore, 6 February 1923, AIA Archives
and Library, Washington, DC).
|
|
1940-1941
|
Works
Progress Administration, under the guidance of the National Park
Service, spent nearly $125,000 on restoration of the building. Replacement
of exterior millwork and interior floor. Removal of stairway and restoration of the Chestnut Street entrance. Refinishing
of interior walls, ceiling and millwork. Cleaning and waterproofing
exterior walls and steps (products used not specified). Roof repaired.
|
|
1942
|
Exterior
marble cleaned and waterproofed (No methodology given, Old Philadelphia
Custom House, 1947, INHP Archives). Photographs
show that the columns and the ashlar of
the south façade were cleaned from the bottom up. The northern elevation was
cleaned in a pattern similar to the southern façade around
the same time. The eastern and western sides were cleaned in sections starting at the northern and southern
ends and working towards the middle (Photograph, May 1942, Photographic
Archives, INHP).
|
|
1961
|
Recommendations
to clean marble with water and brushes. More
difficult areas to be steam cleaned (not more than 100 psi). The
most difficult areas cleaned with hand brushes, 100
psi steam, and sand abrasive. On
an annual basis, exterior was to be cleaned with water and fiber
brushes (Grant Simon, Report on the Preservation of the Exterior
Masonry of the Buildings, INHP
Archives).
Marble
repair recommendations. Removal of defective pointing
and repointing. Loose or soft marble removed and replaced
with “colloidal material.” Incipient seams found with light tapping
from mallet, cleaned and sealed with colloidal materials. Spalled
ashlar replaced by either marble inserts or colloidal material. Today,
yellow patches on columns suggest that some repair recommendations
followed (Grant Simon, Ibid.).
|
|
1963
|
“P-56
Brick and Stone Cleaner” was used on old city hall in experiment;
active ingredient was ammonium fluoride (Gary Dysert,
A Report on the Use of Fluoride Brick and Stone Cleaners,
INHP Archives). The
test was conducted on 17.3 square feet
of dressed stone at Independence Hall. Two coats applied, dwell
time ½ hour, and rinsed off with water and scrubbed with a stiff
bristle brush. Microscopic examination detected a “white haze” residue,
which was successfully neutralized using
a solution of sodium bicarbonate.
|
|
1964-1972
|
Replaced
marble sham doors and windows that were removed
in 1850. Replaced iron doors to vaulting areas with wooden doors,
as heavy corrosion had taken place. Replaced marble removed in 1864
from three south windows on the second floor of both east and west
side were enlarged and extended into the architrave by inserting
an additional sash above the normal window level. Replaced marble
removed in 1864 when small windows were added
to the second floor of the central projection of east and west exterior
walls. Replaced fill in front south windows. Cleaning
of marble exterior with fluoride solutions and clear water. Due
to the severe exfoliation of the exterior columns, temporary clamps
were installed until a decision was made
whether to replace columns or repair condition.
|
|
1964
|
Piece
of marble fell from top of column on east and north façade, (Photograph,
21 January 1964, Photographic Archives, INHP).
Architect
reported that Second Bank was being cleaned
with “Fluoride solutions and clear water.” The steps on the northern
and southern facades were replaced with
marble (Joe Petrak, July 1964, Historic
Structure Report). Penny Batchelor reported that fluoride solutions
were used with soft bristle brushes and rinsed
with clear water (P. Batchelor, “Census of Treated Historic Masonry
Buildings,” Bill Brookover’s Files, 1982).
North façade cleaning: first scaffolding erected on the
eastern side of the portico. Started
at apex of raking cornice and proceeded down to columns and ashlar
stones.
South
façade cleaning: scaffolding first set up on the west side of the
façade, and then pediment was cleaned from top to bottom before
moving on to clean the columns and ashlar
from top to bottom. No photographs were found depicting any cleaning
on the east and west facades beyond the sides of the porticoes (Photographs,
July-August 1964, Photographic Archives, INHP).
Large
detached portion of shaft of northwest column of north façade clamped
in place before being repaired. “Extensive
repairing or partial replacement will be required” (Joe Petrak,
July 1964, Historic Structure Report, INHP
Architectural Library). Today, yellow patches indicate repair,
possibly epoxy.
|
|
1965
|
Reconstruction
of missing panels and terraces using new marble. “Some
spalling at new marble work due to hard
mortar used” (P. Batchelor, Census of Treated Historic Masonry Buildings,
1982, Bill Brookover’s Personal Files). The
1964 specifications of the Second Bank did not mention which type
of mortar should be used (“Specifications: Rehabilitation and Restoration
Second Bank of the United States,” INHP,
Philadelphia).
|
|
1966
|
“Clear-stone”
silicone applied on entire masonry as water repellant, made by Hydrozo Corp. (P. Batchelor, Census of Treated Historic
Masonry Buildings, 1982, Bill Brookover’s
Personal Files).
|
|
1969
|
Joe
Petrak reported that the siliconate
Hydrozo ‘Clearstone’
was used for waterproofing. The marble was
cleaned before application (Weekly Report, INHP
Archives). Penny Batchelor reported that the Clearstone
contains 2 ¼% siliconate solids as produced by General Electric Co., Silicones
Division (First Bank of the United States, HSR).
|
|
1970s
|
Second
Bank adapted for National Portrait Gallery. Museum quality HVAC
system and other new internal systems installed.
|
|
1971
|
Photograph
shows a workman using an artist’s paint
brush to removed spray paint vandalism on north façade. No information
on what cleaning agent was used (Photograph, June 1971, Photographic
Archives, INHP).
|
|
1972
|
Contract
and construction negotiations. Where
necessary, exterior marble sills to be built up
with concrete patches to original profiles so that water runs off
sills. Concrete to be used: weld-crete
from Larson Products Corp., Rockville, Maryland. Used
in “fortified topping process, which allows feather edging.
Mix one part weld-crete to three parts
water. Use in place of water as an admix
to the cement mix. The final product is to match the original stone
sills in color and texture. Surface preparation: dress the original
sills down to the firm stone.” (Contract, Graig
Norrison Notes, Meeting with Mike Callaghan at Callaghan
Marble Shop, 1908 Parish Street, Historic Architect Files, INHP). Today, there are remains of what appear to be concrete
patches on the lowest south portico windows.
|
|
1973
|
Revised
specifications for the Adaptive Restoration of the Second Bank.
Marble to have tooled weathered surface
or rubbed sand surface. Repairs would have deteriorated sections
carefully cut and replacement dutchmen
epoxied tightly in place. Marble to be set with plaster
of Paris mortar backed with cement plaster and metal lath. Pointing to be lime mortar (with one part lime putty, three parts
clean white fine sand) for new fireplace work. Specifications
are for work intended rather than actual work. (Specifications
for Second Bank, 1 February 1973, Historic Architects File, INHP Archives).
12
December: “Cleaning Interior polished marble in Main Banking Room.
Marble cornice stone to be cleaned with FINOLA
Abrasive Scouring Powder made by Masury
Columbia Co., Melrose Park, Ill.
Mixed with water and scrubbed with steel wool. Marble columns and
capitols did not clean well with the above cleaner. Instead, this
stone was cleaned with Wyandotte Detergent Powdered Abrasive Cleaner. Manufacturer
not mentioned. Add this powder to a 5 to 1 mix of water and Clorox
– adding until a cement paste is made. Trowel onto the stone, and
let mixture sit for 24 hours or more. It will absorb and draw out
the penetrated dist. Wash off with clean water and a bristle brush”
(P. Batchelor, Notes from Historic Architect Files, INHP).
|
|
1974
|
Photograph
showing “original column capitol after marble had been cleaned with
a poultice” (Photographic Archives, INHP).
|
|
1975
|
Photograph
documents yellow patches suggesting epoxy repairs on a north portico
column. (Historic Architect’s Files, INHP).
P. H. Batchelor noticed that a “rather sizable”
piece of marble was on the verge of spalling
off from the column next to the west on the north façade.
“The piece is below waist level facing northwest.” She suggested
that the piece could be secured “with an epoxy glue used for stone
repairs” on the First Bank at the west door enframement
(Memorandum from P.H. Batchelor HPT,
to the Superintendent, INHP, 10 November
1975, Historic Architect Files, INHP). A
note adjacent to this memorandum mentioned both clearstone
contgy (?) and Akemi as an adhesive for
stone repairs that could be mixed with
marble dust. Also jotted down were: spezial
fabrik, erich, and chem-techn (Historic Architect’s Files, INHP).
|
|
1982
|
Recommendations
were made by Seymour Lewin
to arrest further deterioration of columns by working a thick, slaked
lime-cement slurry into areas of severe material loss. Lewin
specified that the “proportion of slaked lime to cement must be
adjusted so that the coefficient of thermal expansion of the mixture,
after curing, must be low, so that any – even small – mismatch in
the thermal coefficient will not result in the patch enlarging the
defect it was intended to heal.” Whether this treatment was
carried out by Lewin or not is
not recorded in the NPS record, although Park Service officials
deny that any of the recommendations proposed by Lewin
were actually carried out. Officials believe that the patches in
the north and south façade columns were made
along with other 1960s repairs, and that they are of incompatible
cementitious nature.
|
|
1983
|
Photograph
showing staining by both pigeon debris (guano) and pigeon control
substance, “Roost-No-More” (Bill Brookover,
Personal Files).
|
|
1985
|
Bill
Brookover inspected the scratched graffiti with the words
“George W. 1776” carved into a column in the north portico. The
lightly scratched marble surface was considered easily removed with soft bristle brushes and
water (Memorandum from Bill Brookover
to File, Personal Files). Today, some random scratches are visible.
|
|
1986
|
8 May:
“Small piece of marble has been epoxied
into position. Strap holds piece in position while epoxy sets.
South portico.” (Description of photograph, Bill
Brookover, Photographic Archives, INHP). Type
of epoxy neither documented nor clearly remembered. May
be a common brand name with a set time of 5 or more minutes. No
injecting of drilling. Several fallen pieces of stone were epoxied back in place from
1983 to the present without documentation. Patches currently done
with Dugan limestone patches with a polymer bonding agent. To prepare patch, the shallow areas
of the damaged stone cut away with a four inch diamond blade to
insure a good key (Frank Doyle, stone mason).
13 August: Recent maintenance procedures. Pigeon
debris “cleaned” with city water on north and south portico paving. The
dirty rinse water washed down the steps and over the west edge of
the portico. As a result, the debris deposited on the stair risers,
the west wall of the portico, and the terrace paving and wall (Memorandum
from Bill Brookover, Historical Architect,
to Ross Flanagan, general Foreman on 8/13/86,
Bill’s Files). Today, dark deposits near the bottom of the north
and south portico ashlar indicate that
dirty water also splashed against the portico walls and columns.
7 October:
John Kornich found a piece of marble from
the Second Bank on the west end of the north portico. Believed
to be part of the cornice (Report to Historic Architects, INHP).
|
|
1989
|
28
April: Two pieces of marble found at south façade in alley way and
on porch near south portico column. Believed to have fallen from
base of the column (Historic Architects report, INHP).
|
|
1992
|
30
January: Calcium chloride used as de-icing salts on steps and walkways
at Second Bank (Memorandum from District Ranger to Safety Office,
Brookover Personal Files). Rising damp noted in 1995 inspection.
|
|
1994
|
Bird
netting installed. Pigeon debris reduced. (Conversation
with Bill Brookover, 30 August 1985).
|
|